DAR ES SALAAM: PUBLIC investment is justified by the benefits it brings to citizens, not merely by the money allocated, contracts signed or funds disbursed.
The Vice-President, Deogratius Ndejembi’s concerns over delays in infrastructure projects in Mbeya Region therefore raise an important question: Are taxpayers getting value for money? During his working visit, Mr Ndejembi expressed dissatisfaction with the slow progress of the 29-kilometre Nsalaga (Uyole)-Ifisi four-lane road project, which was 45.67 per cent complete despite substantial financing.
He also questioned why some roads remained closed, inconveniencing motorists, traders and residents, even after officials had been instructed to reopen them.
These concerns go beyond construction schedules. Prolonged roadworks disrupt economic activity, increase transport costs and expose businesses and households to avoidable difficulties.
Where implementation falls behind schedule, it’s the people who bear the cost while the anticipated benefits of public investment remain out of reach.
The project, valued at 183.708bn/-, illustrates why financial commitments must be matched by measurable progress.
The Vice-President said the contractor had received an advance payment of 20bn/- and demonstrated access to another 20bn/- through a bank.
Although financing alone does not establish how much work should have been completed, it raises legitimate questions about the relationship between resources available, contractual obligations and actual performance. Value for money requires more than spending within an approved budget.
It means delivering the promised infrastructure at a reasonable cost, to the required standard and within the agreed timeframe.
A completed road must also be durable, safe and capable of supporting the economic activities for which it was intended.
Effective supervision is therefore essential. Project managers and supervising authorities must verify progress, identify bottlenecks early and ensure contractors meet their obligations.
Reports to senior officials must be accurate, while procurement and contract-management procedures should provide clear grounds for corrective action where performance falls short.
Mr Ndejembi’s unannounced inspection, after finding roads still closed despite earlier instructions, underscores the need to verify official assurances against conditions on the ground.
ALSO READ: PCCB smells a rat in 913 out of 1,864 monitored public projects
Where negligence or deliberate misrepresentation is established, appropriate action should follow due process.
Accountability, however, should extend beyond disciplinary measures to correcting implementation failures and preventing their recurrence.
The other projects reported in Mbeya also warrant close monitoring. The Katumba-Lupaso road was 6.6 per cent complete, while the MbakaKibanja road stood at just 0.3 per cent.
Such figures require context, including contract commencement dates, scheduled milestones and reasons for the reported progress, before firm conclusions can be drawn. Ultimately, citizens need functioning infrastructure, not repeated promises.
The government must strengthen project monitoring, enforce contractual obligations and disclose progress against clear milestones.
Public money is scarce, and every shilling committed to development should produce the greatest possible public benefit.
The post Public projects must deliver value for money appeared first on Daily News.
Public projects must deliver value for money

This story was originally published by Daily News.
Read the full story at Daily NewsRelated stories
NewsIcoT yatakiwa kuongeza wataalamu ujenzi
MOROGORO: Serikali imesema itaendelea kuiimarisha Taasisi ya Teknolojia ya Ujenzi (ICoT), ili kutayarisha wataalamu wengi wenye ujuzi na umahiri watakaoweza kujiajiri na kuajirika kikamilifu katika utekelezaji wa miradi mbalimbali ya maendeleo nchini. Katibu Mkuu wa Wizara ya Ujenzi Balozi, Aisha Amour amesema hatua hiyo inalenga kuongeza upatikanaji wa mafundi sanifu na wataalamu wa kada mbalimbali…
NewsKampuni za Amerika zashinda zabuni kuchimba madini Kwale
MUUNGANO wa kampuni nne za Amerika umeshinda zabuni ya kuendeleza uchimbaji na uchakataji wa madini-adimu na niobium katika eneo la Mrima Hill, Kaunti ya Kwale, ambayo thamani yake inakadiriwa kuzidi Sh6 trilioni. Waziri wa Madini Hassan Joho alitangaza Frontier Minerals Consortium kuwa mshindi wa zabuni hiyo ya matrilioni ya fedha baada ya mchakato wa tathmini na ukaguzi wa ununuzi kukamilika. Ushindi huo unaipa Amerika nafasi muhimu katika sekta ya madini ya kimkakati nchini Kenya, huku ikiendelea kushindana na China kudhibiti upatikanaji na uchakataji wa madini hayo duniani. Kampuni zinazounda muungano wa ushirika huo ni Frontier Minerals LLC, Bunker Hill Mining Corp, ReElement Technologies na American Resources Corporation. Kila kampuni ina utaalamu wake katika uchimbaji, upatikanaji wa madini adimu, uchakataji na usafishaji wa madini muhimu kwa viwanda vya kisasa. Madini ya niobium katika Mrima Hill hutumika katika utengenezaji wa vifaa vya anga, huku madini-adimu yakihitajika katika magari ya umeme, vifaa vya kielektroniki, mitambo ya upepo, silaha za kisasa na teknolojia ya Akili-Unde. Kampuni ya ReElement Technologies tayari imevutia uwekezaji wa serikali ya Amerika wa Dola milioni 25 (takriban Sh3.2 bilioni) uliotangazwa mnamo Julai 2026 kusaidia uwekaji wa vifaa katika kiwanda chake cha kusafisha madini adimu katika jimbo la Indiana, Amerika. Uwekezaji huo ni sehemu ya juhudi za Amerika kupunguza kutegemea China, ambayo inaongoza duniani katika uchakataji wa madini hayo. Kampuni saba ziliorodheshwa kushindania mradi huo mnamo Julai, zikiwemo kampuni mbili za China, miungano miwili ya kampuni kutoka Amerika, muungano wa Australia na ubia wa Kenya na Uingereza. Kampuni za China baadaye zilijiondoa. Joho alisema kushinda zabuni hakumaanishi kampuni hiyo inaweza kuanza uchimbaji mara moja. Inapaswa kwanza kupata leseni zinazohitajika, kutekeleza masharti ya kisheria na kushirikisha jamii ya eneo hilo. Serikali pia imesisitiza kuwa madini hayo hayapaswi kuuzwa yakiwa ghafi, bali yaongezwe thamani nchini kupitia viwanda vya uchakataji. Muungano huo umesema utajenga uwezo wa kuchakata madini nchini, hatua inayoweza kuunda nafasi za ajira na kuongeza mapato. Kwa Kenya, mradi huo unatoa fursa ya kupanua uchumi ambao kwa muda mrefu umetegemea kilimo na utalii. Mapato ya sekta ya madini yalipungua kutoka Sh35 bilioni mwaka 2022 hadi Sh20.3 bilioni mwaka jana, hasa kutokana na kufungwa kwa migodi ya madini ya titanium katika Kaunti ya Kwale. Hata hivyo, mafanikio ya mradi wa Mrima Hill yatategemea uwekezaji, masharti ya leseni na namna jamii zitakavyoshirikishwa na kunufaika.
News2027: ACF warns of emerging political violence, urges restraint
…Forum urges Tinubu, governors to ensure fairness to opposition By Ibrahim Hassan-Wuyo The Arewa Consultative Forum (ACF) has raised concerns over emerging signs of political violence ahead of the 2027 general elections, urging political leaders, security agencies and Nigerians to embrace restraint and protect democratic values. The forum warned that provocative demonstrations, stone-throwing, abusive chants […]
NewsUtatu haki jinai watakiwa kuimarisha ushirikiano
ARUSHA: Mwanasheria Mkuu wa Serikali, Hamza Johari, ameitaka Taasisi ya Kuzuia na Kupambana na Rushwa (TAKUKURU), Ofisi ya Taifa ya Mashtaka (DPP) na Jeshi la Polisi, kwa kushirikiana na taasisi nyingine za haki jinai, kutekeleza majukumu yao kwa uadilifu, uaminifu na uzalendo ili kujenga imani ya wananchi kwa Serikali. Johari amesema hayo leo jijini Arusha…