ARUSHA: THE Tanzanian government has released 19bn/- to compensate residents whose properties and land have been affected by road construction projects being implemented in Arusha ahead of the 2027 Africa Cup of Nations (AFCON), with contractors directed to accelerate construction works.

Minister for Works Masanja Kungu Kadogosa issued the directive during an inspection of ongoing AFCON-related road projects in Arusha, instructing the Tanzania National Roads Agency (TANROADS) to begin paying the affected residents immediately.

He said the compensation funds, provided under the leadership of President Samia Suluhu Hassan, were already available and there was no reason for further delays in settling payments to eligible residents.

The minister directed TANROADS to ensure the payments were made within two to three days to enable residents to receive their rightful compensation and allow contractors to continue with construction activities without interruptions.

Kadogosa emphasised that the Government’s investment in the road projects was not solely intended to facilitate the hosting of AFCON 2027 but also to deliver lasting infrastructure benefits to residents beyond the tournament.

During the inspection, he expressed satisfaction with contractors’ preparations and commended TANROADS, through its TECU unit, for supervising the implementation of the projects.

He further directed contractors to increase the number of equipment, machinery and workforce at construction sites to accelerate progress, insisting that works should continue around the clock, including during the day and night.

ALSO READ: Mikumi airport takes shape ahead of AFCON

Kadogosa said effective utilisation of the available time was essential to ensure the projects were completed within the planned schedule ahead of the continental football tournament.

For his part, TANROADS Arusha Regional Manager, Engineer Reginald Massawe, assured the minister that contractors had completed the mobilisation of equipment and machinery at the project sites by 100 per cent and deployed the required technical personnel.

He said the measures had contributed to increased construction activities, with works currently progressing during both daytime and night hours.

Meanwhile, Engineer Hophine Mollel, the TECU project supervisor for the 70-kilometre Mbauda-Losinyai Road, said the 13-kilometre section earmarked for AFCON 2027 preparations had reached 54.4 per cent completion.